Category Archives: Ground Floor
Week Thirty one to end October ’12
There were apologies here because I hadn’t kept this up to date. So some progress now (end May 2013) at long last! Last autumn and winter we really got very busy indeed and keeping this up to date was a task … Continue reading
Weeks Seventeen and Eighteen
Another rush of progress, but in curious fits and starts. One moment the site is full of activity, the next there’s hardly anyone here doing anything. We’ve made it clear that we’re not aiming for a particular date, so we … Continue reading
Posted in Cladding, Ground Floor, Thermal mass, Windows
Leave a comment
Weeks Fifteen and Sixteen
The week after Easter was only a short week, but seems to have continued very busy. Tacking—putting up plasterboard—got underway. The intention is to tack the downstairs ceilings first. This will allow the Warmcel 500 to be blown into the … Continue reading
Week Six
They have had a really rotten week, last week, with the second half being really cold and wet—quite miserable. This photo, taken in the middle of this week shows how well they’ve got on and the weather’s better at the … Continue reading
Posted in Ground Floor, Precut wood
Leave a comment