Category Archives: Ground Floor

Week Thirty one to end October ’12

There were apologies here because I hadn’t kept this up to date.  So some progress now (end May 2013) at long last! Last autumn and winter we really got very busy indeed and keeping this up to date was a task … Continue reading

Posted in Electrics, Ground Floor, Plumbing, Solar PV, Solar thermal, Ventilation, Zero Carbon House | Comments Off on Week Thirty one to end October ’12

Weeks Seventeen and Eighteen

Another rush of progress, but in curious fits and starts.  One moment the site is full of activity, the next there’s hardly anyone here doing anything.  We’ve made it clear that we’re not aiming for a particular date, so we … Continue reading

Posted in Cladding, Ground Floor, Thermal mass, Windows | Comments Off on Weeks Seventeen and Eighteen

Weeks Fifteen and Sixteen

The week after Easter was only a short week, but seems to have continued very busy.  Tacking—putting up plasterboard—got underway.  The intention is to tack the downstairs ceilings first.  This will allow the Warmcel 500 to be blown into the … Continue reading

Posted in Foundations, Ground Floor, Solar PV, Solar thermal, Thermal mass, Underfloor heating, Windows | Comments Off on Weeks Fifteen and Sixteen

Week Six

They have had a really rotten week, last week, with the second half being really cold and wet—quite miserable.  This photo, taken in the middle of this week shows how  well they’ve got on and the weather’s better at the … Continue reading

Posted in Ground Floor, Precut wood | Comments Off on Week Six