Monthly Archives: April 2012

Weeks Fifteen and Sixteen

The week after Easter was only a short week, but seems to have continued very busy.  Tacking—putting up plasterboard—got underway.  The intention is to tack the downstairs ceilings first.  This will allow the Warmcel 500 to be blown into the … Continue reading

Posted in Foundations, Ground Floor, Solar PV, Solar thermal, Thermal mass, Underfloor heating, Windows | Comments Off on Weeks Fifteen and Sixteen

Weeks Thirteen and Fourteen

 Got rather behind with this – not keeping it up to date – sorry.  Here goes: OK, things have got pretty hectic.  First was Alex and Andy the electricians arriving—as expected.  What I’d failed to do was ask what I … Continue reading

Posted in Electrics, Solar PV, Solar thermal | Comments Off on Weeks Thirteen and Fourteen

Weeks Eleven and Twelve

Two very hectic weeks.  16 sheets of 3 ply appeared.  These are for the soffits of the deep overhangs—please paint them—one side only.  This seemed to be just the job for spray painting.  Lean them up against the black barn … Continue reading

Posted in Electrics, Plumbing, Roof, Thermal Store, Windows | Comments Off on Weeks Eleven and Twelve